KU study examines how states are approaching data center development – and there’s a few things Kansas could learn

photo by: AdobeStock

Data centers to power artificial intelligence have been built on agricultural land near Dublin, Ohio, pictured in this undated photo.

A new University of Kansas study examines how states — including Kansas — are regulating data center development as the artificial intelligence industry grows rapidly.

The study was published in Frontiers in Sustainable Cities, and it evaluates policies about data centers from all 50 states with at least one city or county within each state. Its findings show different approaches to policies surrounding these large-scale developments, and the researchers generally selected jurisdictions with the highest numbers of data centers in their respective states.

“The challenge of data centers, as with the rapidly evolving wind or solar power sectors, is as the federal government shifts back and forth between pro- and anti-stances,” study co-author Ward Lyles, professor of urban planning and Indegious studies at KU, said in a press release. “You also have 50 states and 3,000 counties across the country that get a say.”

Researchers collected state policies from 2025 to early 2026, focusing on two areas: state-level incentives and legislation intended to attract or limit data center development, and local zoning regulations designed to control where facilities are built and how they affect surrounding communities.

Some states, including Tennessee, Louisiana and Ohio, encourage development through long-term tax exemptions and minimal land-development requirements. Meanwhile, others have taken a more restrictive approach through moratoriums, reduced tax incentives and environmental planning. At the time of the study, New York, Maryland and New Hampshire had proposals for statewide moratoriums.

Kansas has taken a somewhat different approach from states that have passed moratoriums or legislation overriding local zoning authority for data centers. The state has encouraged large-scale investment, but has left land-use decisions to local governments.

The most significant piece of Kansas legislation related to data centers is Senate Bill 98, which passed in 2025. The law established a 20-year state and local sales and use tax exemptions for qualifying data center projects.

More locally, Douglas County currently has a “de facto pause” — which acts similarly to a moratorium — in place as it continues to research data center regulations. The county will not accept any data centers project applications until the regulation process is complete.

The City of Lawrence recently placed a 24-month moratorium on data center development in July so planning staff can study data centers impacts and draft new rules. In October, city commissioners voted to require special use permits for future data center projects. This means data centers are no longer allowed “by right” in industrial zones, as they were previously.

The academic study by KU researchers — who also were joined by researchers from Iowa State and Arizona State — finds that economic development policies are advancing faster than the regulations designed to protect local communities. States are competing to attract billions of dollars in investment, while cities and counties are left dealing with many of the consequences.

WHAT’S HAPPENING IN KANSAS

The study did not dive into the specifics of how Kansas is regulating data centers. Kansas, though, has made some moves in encouraging data center development, but leaves a lot of regulations up to local communities.

For data center projects to qualify for the state’s SB 98 incentives, the developments have to meet some requirements, such as:

• Investing at least $250 million in eligible data center costs within five years of beginning operations.

• Create at least 20 new full-time jobs for Kansas residents within two years of beginning operations.

• Commit to purchasing electricity from the local retail utility for 10 years.

• Adopt water conservation, reuse and replacement practices through a comprehensive water plan.

• Receive approval through the Kansas Intelligence Fusion Center’s review process.

The law also allows the state to suspend or terminate the tax exemption, or require repayment of some or all of the benefits, if a company fails to meet its commitments.

Last year, the Kansas Corporation Commission approved a large-load electricity rate plan for Evergy customers. The plan applies to new facilities with a projected peak demand of at least 75 megawatts — which is approximately equivalent to what 50,000 homes would use in a month. The special rate also applies to certain existing facilities that expand their demand to that amount.

The purpose is to help prevent existing customers from bearing the costs of infrastructure and electricity demand associated with the large energy-users. While Kansas has attempted to address some of the potential electricity-cost impacts, there are other things the state could learn from other communities.

HERE’S WHAT KANSAS CAN TAKEAWAY

Other states and local governments have adopted different measures to address the potential impacts of data centers, offering examples of policies Kansas could consider for its own regulations.

When it comes to electricity, the city of Minneapolis can negotiate infrastructure upgrades with developers before granting special-use permits for data center projects. This is in place to avoid having residents and businesses bear the costs of improvements that are needed primarily for a new development.

In addition, Linn County, Iowa requires written verification from power providers to support development approvals in order to determine sufficient electricity infrastructure is available before a project is approved.

While Kansas requires the projects receiving benefits to adopt water conservation and reuse practices, the legislation does not prescribe a specific cooling technology or establish a daily water-consumption limit.

Other states — like Utah — have more specific regulations towards water use. Rather than simply requiring a developer to commit to water conservation practices, Utah requires certain cooling technologies for new data centers. Developers must use closed-loop or dry cooling systems.

Prince William County in Virginia has also been trying to accomplish two things at once: make it easier for data centers to locate in designated industrial areas while requiring developers to take steps to protect nearby residential neighborhoods.

To do that, the county established a special zoning classification within industrial zoning called the Data Center Opportunity Zone Overlay District. The county requires sufficient electricity infrastructure in the proposed development areas and concentrates data center development in appropriate locations rather than allowing them to spread throughout the county.

RESEARCHERS’ CONCLUSIONS

The researchers said that local governments will need to move beyond traditional zoning practices when regulating modern data centers supporting the AI boom.

While there are some steps communities can take to address the visual impacts from residential areas close to the industrial developments, such as landscaping and screening, those measures do little to address the broader demands these facilities are expected to place on electricity grids, water supplies and wastewater infrastructure.

It is recommended to do more comprehensive planning that considers the cumulative impacts of multiple data centers, rather than evaluating each project on its own.

Additionally, the researchers urge developers to be transparent in their anticipated water and electricity consumption, and communities should have opportunities to understand and participate in decisions that affect their resources.

The researchers say that state governments can create incentives for development while leaving local communities responsible for managing the consequences. The study argues that better coordination between state and local governments is necessary to ensure the economic benefits do not come at the expense of environmental resources or a community’s quality of life.