Second phase of $46 million renovation will open soon at Lawrence High School
photo by: Mike Yoder
While standing in a newly renovated classroom on the second floor of Lawrence High School, school board member Carole Cadue-Blackwood said it felt like she was somewhere else.
“It’s like a treehouse,” Cadue-Blackwood said, looking out large windows into the trees surrounding the school. “It’s my favorite room.”
On Friday, Cadue-Blackwood and other Lawrence school district officials were touring the newest addition to LHS, which is phase two of an ongoing $46 million expansion and renovation. The southeastern wing of the school, which runs along Louisiana Street, now features a two-story corridor that connects what was originally an annex building with LHS’ main building.
photo by: Mike Yoder
Teachers and students will soon be able to use the new portion of the school, said Tony Barron, the school district’s executive director of facilities and operations. He said the school expects to begin using the handful of new and renovated classrooms and other features as early as Wednesday.
“We’re excited to get into the space,” Barron said.
Much like the first phase of the project, which was completed in the fall, the renovated southeastern wing features many windows that allow an abundance of natural light. The wing will mainly be used for science, social studies and math courses, and it will also house some special education classrooms. It includes new faculty lounges and some small work spaces, as well.
photo by: Mike Yoder
Along with Cadue-Blackwood, board members Shannon Kimball and G.R. Gordon-Ross said they were impressed with the new look.
“It exceeds my expectations,” Kimball said. She thought the natural lighting would provide a more comfortable setting for students.
With the phase two of the 27-month construction project finished, C.J. Armstrong, a Gould Evans architect working on the project, said the vast majority of new construction at the school has been completed.
The rest of the project will mostly focus on renovating existing areas of the school. However, there are still some parts that will involve new construction, such as filling in an area between the school’s main gym and the foreign language hallway to provide more locker room space, Armstrong said.
photo by: Mike Yoder
Barron said there are five more phases of the project remaining, and two of those are scheduled to begin in the next few months.
Phase three of the project is expected to begin shortly after the teachers and students move into the southeastern wing, Barron said. That phase will include renovating the “heart” of the school, which includes the areas where math and social studies classrooms are currently housed. Phase three is expected to finish sometime in the summer, before the beginning of the 2020-2021 school year, he said.
Phase four is expected to begin after Memorial Day and to last until the end of the fall 2020 semester. That phase includes improvements to the library, kitchen and commons area, as well as a renovation of the school’s west gym, Barron said.
The completion of the first phase of the project was delayed because of the discovery of additional asbestos and issues from severe weather, including electrical complications associated with the May 2019 tornado. The delays caused the school district to push back the start of the current school year for both high schools by six days.
The delays also caused construction for phases two and three to be pushed back. Originally, phase two was expected to be finished by the end of the fall semester and phase three was expected to be completed before the end of the spring semester.
Gordon-Ross said he doesn’t expect the same kinds of hiccups in the upcoming phases. The first phase was a much larger construction project, consisting of about 76,000 man-hours, he said. Phase three is expected to be about 40,000 man-hours, giving the construction project more leeway if weather poses any issues, he said.
“Mother Nature is what Mother Nature is, but the likelihood that we run into the same issues we ran into last year is much less,” Gordon-Ross said. “It’s a different situation all around.”
As for the remainder of the project, Barron said it is still on track to be completed by August 2021.
“We’re excited about the next two phases and we’re really comfortable (with) where we’re at,” he said.
photo by: Mike Yoder
photo by: Mike Yoder
photo by: Mike Yoder
photo by: Mike Yoder
Contact Dylan Lysen
Have a story idea, news or information to share? Contact reporter Dylan Lysen:
- • dlysen@ljworld.com
- • 785-832-6353
- • Twitter: @DylanLysen
- • Read other stories by Dylan
COMMENTS