City seeking grant money to improve 23rd and Haskell intersection in preparation for increased traffic from SLT

If there is a special set of scissors out there that have been put aside to cut the ribbon on the completed South Lawrence Trafficway, it may be time to get them out and limber them up. You’ll probably have to knock the rust off of them too. After all, they’ve been sitting unused for more than 20 years.

Obviously, a ribbon cutting for the final leg of the SLT isn’t imminent, but there are more and more signs all the time that people now understand the day is coming. Construction is set to begin this fall, and the road could be open by the Fall of 2016.

The latest signs of preparations for the project are coming out of Lawrence City Hall. Commissioners at their meeting tonight will have three items on their agenda related to the SLT.

The largest is an item to begin the planning of significant upgrades to the 23rd Street and Haskell Avenue intersection.

Commissioners are being asked to submit a grant application to the Kansas Department of Transportation for $1.2 million worth of improvements to the intersection.

The project would include rebuilding the entire intersection with concrete and adding right-turn lanes on 23rd street to accommodate traffic turning both north and south onto Haskell. New traffic signals, storm sewer improvements and sidewalk ramps also would be installed.

The project also would include a widening of Haskell Avenue for the first several feet south of 23rd Street. That widening would make it easier for all of Haskell Avenue to be widened in the future, if traffic demand calls for it.
Haskell likely will become a busier road once the trafficway is completed. The SLT plans call for an interchange to be built where Haskell and the SLT intersect. It will be one of the few places for motorists in eastern Lawrence to get onto the trafficway. The only other two interchanges for the SLT will be at Iowa Street and at the ending point for the SLT, which will be near Noria Road on the far eastern edge of the city.

The city is seeking $900,000 in state grant funding for the project. The city at-large would pay the other $300,000 for the improvements. The city should find out this summer whether it has been awarded the grant. Construction likely would occur in the summer or fall of 2015.

The second project is just a simple repaving of 23rd Street from Iowa to Ousdahl. At first glance, that may not seem to have much to do with the South Lawrence Trafficway, but it does. City officials are trying to get as much work done on 23rd Street as possible because currently 23rd Street also is designated as Kansas Highway 10. That designation means it is eligible for state funding for repaving or other similar work.

But once the South Lawrence Trafficway is completed in 2016, 23rd Street no longer will be designated as Kansas Highway 10, and the full cost of maintaining 23rd Street will fall on the city. At their meeting tonight, commissioners will apply for $200,000 in state funds to help repave the section of 23rd Street. If approved, construction work would take place in the summer of 2014.

That would tie in well with a larger project that already has been approved. A major rebuilding of the 23rd and Iowa street intersection is scheduled for 2014.

The third SLT project on tonight’s agenda is a wetland project. That perked up some ears in this town. One part of the SLT project that some people may have forgotten about is that a whole new east-west city street will be constructed at the same time the SLT is being built.

As most people know, 31st Street will move to the south a bit and become a new four-lane city street. But it no longer will stop at Haskell Avenue. Local officials will build the new 31st Street (it actually may be called 32nd Street) eastward all the way to O’Connell Road.

As part of that project, it is estimated about 4 acres of wetlands on the east side of Haskell Avenue will be disturbed by the construction. If you have followed the history of the SLT, perhaps you have heard that if you disturb wetlands you have to create new wetlands to mitigate the effects.

At tonight’s meeting, city commissioners are set to approve an approximately $25,000 contract with Wilson & Co. to begin creating the plan to mitigate the wetland damage. The working plan is that the city will buy 4 acres of excess property in the area from KDOT and turn the land over to Baker University to create new wetlands. But Wilson & Co. will hold a series of public meetings to get feedback on the issue.

Tonight’s City Commission meeting is set for 6:35 p.m. at City Hall.