When will the intersection at 31st and Iowa be completed?

City Engineer Terese Gorman said: "The contractor believes that it will be late June before 31st Street and 31st and Iowa are totally open to traffic. Even then, all the cleanup will not be done, and the westbound right-turn lane at Iowa will not be constructed because the fuel tanks for that gas station are in the way of the widening and cannot be moved until the gas station is gone. And the gas station is not scheduled to be moved until mid- to late July."