Petition for Judicial Review of Kansas Department of Health and Environment Denial of Permit Application Under K.S.A.§ 65-3012(A)

Petitioner, Sunflower Electric Power Corporation ("Sunflower"), hereby petitions this Court pursuant to K.S.A. § 77-607 for judicial review of the denial of Sunflower's application to the Kansas Department of Health and Environment ("KDHE") for the issuance of a permit authorizing construction of two new electricity generating units (the "Power Plants") at its Holcomb Generating Station located in Finney County, Kansas (the "Application") by KDHE Secretary Roderick L. Bremby (the "Secretary") on October 18, 2007 (the "Denial Order"), to the extent that the Denial Order was issued by the Secretary pursuant to K.S.A. § 65-3012(a). In compliance with K.S.A. § 60-2101, Sunflower has hereby timely and properly given notice of
this appeal to Respondents.